2023 Operation

Posted: Fri Mar 17, 2023 10:55 am
by dukwon
Full 2023 schedule: https://edms.cern.ch/document/2785501

We are mid-way through the "hardware recommissioning" stage after YETS. This week have been powering tests, handshake tests, beam mode tests etc.

From next week, you can follow along with the commissioning spreadsheet linked at the top of the LPC page: https://lpc.web.cern.ch/

This year the plan is 49 days of commissioning and intensity ramp, 97 days of pp physics from mid-May, 27 days of PbPb physics from late September.

Next YETS will start at the end of October due to the energy crisis.

Lumi targets are anywhere from 60 to 80 /fb for IP1&5, 7 /fb for IP8, 30 /pb for IP2.

Re: 2023 Operation

Posted: Mon Mar 20, 2023 7:05 pm
by jmc2000
153rd LHCC Meeting - OPEN Session
https://indico.cern.ch/event/1254283/

Page 14 of the Status of Accelerator document shows 1.3fb/day for 2023, if I understand things correctly, an improvement from 1.1fb/day for 2022. I was under the impression that it was around 0.8fb/day in 2022.

Jmc

Re: 2023 Operation

Posted: Wed Mar 22, 2023 9:47 am
by dukwon
One of the new collimation crystals (installed at point 7 during YETS) is stuck in the beampipe. This will add a ~week delay to first beams.

Caverns are still closing today. Injection tests scheduled for Friday.

Re: 2023 Operation

Posted: Tue Mar 28, 2023 9:25 am
by dukwon
Beam 1 threaded to IP5 before LBDS problems

Beam 2 successfully circulating

Re: 2023 Operation

Posted: Tue Mar 28, 2023 10:29 am
by dukwon
Both beams

Re: 2023 Operation

Posted: Wed Mar 29, 2023 8:41 pm
by dukwon
FIrst ramp of the year

Re: 2023 Operation

Posted: Wed Apr 05, 2023 2:45 pm
by dukwon
First collisions in 2023 with 450 GeV beams

Re: 2023 Operation

Posted: Thu Apr 06, 2023 7:57 am
by dukwon

Re: 2023 Operation

Posted: Thu Apr 13, 2023 9:26 am
by M.
First collisions at low-beta* - 1.2m.

Followed by the first beta* levelling with colliding beams from 1.2m down to 30cm in ATLAS and CMS.

Re: 2023 Operation

Posted: Fri Apr 21, 2023 11:03 pm
by M.
First Stable Beams @ 1.2m -> 30cm!

Now for the intensity ramp-up...

Re: 2023 Operation

Posted: Wed Jul 19, 2023 7:18 pm
by dukwon
lhc1.png
On Sunday night the LHC experienced an electrical perturbation, causing an RF trip (P4) and several magnet quenches close to P8. As a consequence, the pressure in the insulation vacuum increased, which indicates a possible leak (unsure if it is air or Helium).

Re: 2023 Operation

Posted: Thu Jul 20, 2023 1:46 pm
by dukwon
Rather than doing my own write-up: here's an official one

https://home.cern/news/news/accelerator ... leak-major

Re: 2023 Operation

Posted: Fri Jul 21, 2023 11:58 am
by dukwon
Vibration tests have shown an "a clear anomaly" at a particular interconnect, which is likely where the leak is. X-rays were performed at that location but were inconclusive.
The current plan is to open up the W-bellow at that location on Monday and see what's there.

The longer-term plan will depend on what's found. Coarsely: the repair may or may not require warming up the whole of sector 78. Warming up takes some weeks, cooling down takes about a month, then there's QA, powering tests and training.

Since YETS is meant to start at the end of October, I'm not super optimistic about getting beams back this year.

Re: 2023 Operation

Posted: Mon Jul 24, 2023 5:13 pm
by dukwon
Screenshot from 2023-07-24 19-06-09.png
Screenshot from 2023-07-24 19-06-09.png (12.88 KiB) Viewed 49705 times
This sounds promising and suggests that they might not have to warm up the sector, but we will hear more in the next few days.

Re: 2023 Operation

Posted: Tue Jul 25, 2023 5:01 pm
by dukwon
The leak was indeed found on Monday (1.6 mm hole just about visible in the close-up pic below).
Work is ongoing to replace the damaged bellow. Time is really critical, as the longer this intervention takes, the bigger the risk of damage to the cryo system. If it takes too long, the whole sector will be warmed up and we will not have beam again this year.

The optimistic scenario is to have beams back by early September, recommission with protons, then set up the ion run as planned.
leak_found2.jpg
leak_found3.jpg