Page 1 of 3

October 2021 Beam Tests + 2021/22 YETS

Posted: Fri Oct 15, 2021 7:53 pm
by dukwon
The LHC is currently in "machine checkout": the machine and caverns are closed, all interlocks are cleared, and the beam dump system is armed.

Over the weekend we will have some machine protection tests and short transfer line tests.

Monday 18th Oct should see some beam mode tests (NB: no actual beams).

First beams in the ring since 2018 are scheduled for Tuesday 19th Oct, pending the success of the tests at the weekend. By Wednesday we should have circulating beams.

Re: October 2021 Beam Tests

Posted: Fri Oct 15, 2021 9:21 pm
by DCWhitworth
<incoherent excited noises>

Re: October 2021 Beam Tests

Posted: Mon Oct 18, 2021 10:48 am
by dukwon
~1 day delay over the weekend due to an issue with a UPS (exploded battery).

BIS and LBDS tests took place on Sunday. A vacuum valve controller caused issues and needed replacing.

One klystron on beam 1 needs replacing (takes weeks) but beam tests can go ahead without it.

Today, following some interventions this morning, the accelerator mode should go to "Beam Setup", and the checkout will continue, including transfer line tests.

Tomorrow we should hopefully have beam threading, working up to a first turn, and the following night some "splashes" for the experiments.

Re: October 2021 Beam Tests

Posted: Tue Oct 19, 2021 2:13 pm
by dukwon
Beam 2 has been threaded through the full ring and made >25 full turns in one of the first attempts. Enough to register as a little blip on Page1
lhc1.png

Re: October 2021 Beam Tests

Posted: Tue Oct 19, 2021 3:26 pm
by CharmQuark
:happy-wavemulticolor: :happy-cheerleaderkid: :happy-jumpeveryone: :happy-cheerleadersmileyguy: :happy-cheerleadersmileygirl:

Re: October 2021 Beam Tests

Posted: Tue Oct 19, 2021 4:00 pm
by dukwon
B1 was struggling a bit with high losses, but now it has made an appreciable number of turns (small blue blip!)

One probe in B2 now circulating stably
lhc1.png

Re: October 2021 Beam Tests

Posted: Tue Oct 19, 2021 4:46 pm
by DCWhitworth
So far so good ! Thanks for keeping us updated. Can’t wait to see the big beast back in business.

Re: October 2021 Beam Tests

Posted: Sat Oct 23, 2021 7:18 pm
by 123e443
Beam Dump

Re: October 2021 Beam Tests

Posted: Sat Oct 23, 2021 7:26 pm
by 123e443
LBDS B1 In fault
no beam for a hour a least
https://vistar-capture.web.cern.ch/vist ... 5566609957

Re: October 2021 Beam Tests

Posted: Tue Oct 26, 2021 11:50 am
by dukwon
First colliding single bunches at 450 GeV in 'adjust' at all IPs! First stable beams scheduled for tomorrow
lhc1.png

Re: October 2021 Beam Tests

Posted: Wed Oct 27, 2021 8:08 am
by dukwon
Now stable beams!
lhc1(2).png

Re: October 2021 Beam Tests

Posted: Tue Nov 02, 2021 1:14 pm
by dukwon
Aperture scans found a "unidentified lying object" (ULO) at 21L3. A bump of a few mm is sufficient to clear it with no problem.
ulo_2.jpg
ulo_2.jpg (40.19 KiB) Viewed 21992 times
This mirrors the 2015 post-LS1 commissioning, where a ULO was found at 15R8, which turned out to be a piece of plastic

Re: October 2021 Beam Tests

Posted: Tue Nov 02, 2021 1:52 pm
by dukwon
Highlights from the beam tests:
  • High machine availability throughout the tests (~90%)
  • 40 hours of stable beams over 5 nights (6 hours planned)
  • All key instruments working, mostly from day 1
  • ULO found at 21L3
  • Opportunistic ramp to 3.5 TeV with pilot beams

Re: October 2021 Beam Tests

Posted: Tue Nov 09, 2021 1:07 pm
by dukwon
The "ULO" has been identified as a buckled RF finger, so sector 23 will be warmed up for an intervention. This delays the restart by several weeks. (However, better to catch it now than then!)

Re: October 2021 Beam Tests

Posted: Thu Nov 11, 2021 9:53 pm
by Tau
Frustrating to hear the news, but I've been wondering what was going on.
Thanks for the update.